China National Stadium
- "Bird's Nest"
The National Stadium, known as the
"Bird's Nest", serve as the main venue of
the 2008 Beijing Olympic Games. It is located in the
Olympic Green and occupies 21.4 hectares. It stretches
333 meters from north to south and 298 meters from east
to west, covering an area of 258,000 square meters.
The National Stadium is 68 meters high and holds 91,000
seats, including 11,000 temporary seats. The construction
of the National Stadium began in December of 2003.
The venue hosted the opening and closing
ceremonies of the Beijing Olympic Games and Paralympic
Games, the track and field competitions, and the football
finals. After the Olympics, the stadium will become
a large-scale sports and entertainment facility for
the residents of Beijing -- an architectural landmark
and Olympic legacy.
The National Stadium is surrounded
in a sort of membrane. Unlike China's National Aquatics
Center, or "Water Cube," another Olympic venue
which is also surrounded in this membrane, the Bird's
Nest version is curved and double-layered, offering
gracefully decorative soundproof, wind-proof, rain-proof,
and even UVA protection to its already impressive body.
The outer layer of membrane, completely constructed
in November of 2007, was created using 884 individual
ETFE panels, covering a total of 38,500 square meters.
The inner layer consists of PTFE material. 1,044 panels
take up 53,000 square meters of area, whose main purposes
are to better the acoustics in the stadium and to support
the equipment within the steel frame.This special membrane
can also help lighting within the stadium and effectively
diminish glare and shadowing, allowing for a more favorable
competition environment.
The main body of the National Stadium
has a design life of 100 years. Its fire resistance
capability is first-rate, and it can withstand an 8-magnitude
earthquake. The water-resistance capability of its underground
project is also first-rate.
The main body's elements support each
other and converge into a grid formation, just like
a bird's nest with interlocking branches and twigs.
The construction of the National Stadium
followed the PPP mode (Private + Public + Partnership
), and it is co-owned by the Beijing State-Owned Assets
Management Co. Ltd (BSAM), who shares 58 percent of
the total assets, and the China International Trust
and Investment (CITIC) Consortium, who holds the rest
of the assets.
The National Stadium is a complex
structure, posing great difficulties for its designers
and constructors.
1. Large and heavy steel parts
The fracture surface of the largest truss column --
the major load-bearing component of the roof structure
-- measures 25m x 20m, with a height of 67m. The maximum
weight of a single column is 500 tons. The main truss
is 12m tall. The maximum span between and through the
two columns amounts to 145.577+112.788m, and the maximum
span between the two trusses stands at 102.39m. Each
truss column is of great bulk and weight, and so are
the main trusses.
2. Complex nodal joints
Because the structural elements in the project are box-typed,
many elements intersect spatially among the steel parts.
Besides, the complex nature of secondary structures
has resulted in the diversity of nodal joints of the
main structures, requiring accurate and sophisticated
manufacturing and installation.
3. Tight schedule
In addition to the huge workload, the allotted construction
period is short. Having started on December 24, 2003,
the project is expected to be completed by the end of
2007, with the inauguration time scheduled for March
2008. Therefore many operations have to be conducted
on a limited terrain, causing a very tense situation.
4. The hoisting work extended across
the winter and spring, so the workers have had to defy
both rainy and cold conditions in the winter to continue
their work.
The workers have overcome tremendous
engineering and technical challenges in the process
of construction:
1. Difficult work arrangement
They need to do very detailed research of operations
and follow meticulous arrangements to complete various
kinds of work within a limited workspace.
2. Difficult hoisting of steel parts
To facilitate the assembly of the steel parts, the workers
have to use a prone position to assemble the truss columns,
which requires a turnover process before they are hoisted.
The choice of the hoist points and lug hooks pose great
difficulties in the face of bulky and cumbersome steel
parts, and the change of pulling stress from three directions
must be taken into consideration. The workers need to
meticulously rectify angles and positions of the box-typed
sectional parts to ensure accurate abutment during the
hoisting process.
3. Difficult stabilizing process
They also have to fight the heavy wind load and keep
the stability of the steel parts by following a strict
working order and use lateral stability measures including
the use of anchoring method and wind-holding ropes.
4. Difficult welding
The welders not only face a huge work volume, but also
have to work on both the thin steel sheets and thick
steel slabs, on high-strength and cast steel elements,
and take downward, vertical or overhead positions while
welding. They face temperature changes, steel deformation
and intensive labor. They need to work above ground,
in winter rain and under windy conditions.
5. Difficult installation
The workers face difficulties in ensuring accurate installation
as the steel parts and the related gigs and fixtures
can be deformed easily under their own dead weight and
the change of temperatures. The workers must take pre-installation
measures to rectify and relieve the errors that might
occur in the process of installation.
|